To avoid vapourisation, pipe lines are laid over the ridge so that these are above the hydraulic gradient line, not more than« Back to Previous Page

A. 2.4 m B. 6.4 m C. 10.0 m D. 5.0 m.
Posted by Civil Engineer
Asked on August 12, 2016 1:20 pm
0

B.
6.4 m

Posted by Civil Engineer
Answered on August 12, 2016 1:21 pm