In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted. The load is gradually removed and the consequent rebound is measured. For a safe pile, the net settlement (i.e. total settlement minus rebound) per tonne of test load should not exceed« Back to Previous Page

A. 10 mm B. 15 mm C. 20 mm D. 25 mm E. 30 mm
Posted by Civil Engineer
Asked on August 20, 2016 12:53 pm
0

D. 25 mm

Posted by Civil Engineer
Answered on August 20, 2016 12:54 pm