The optimistic, most likely and pessimistic time estimates of an activity are 5, 10 and 21 days respectively. What are the expected time and standard deviation respectively ?« Back to Previous Page

A. 12, 3 B. 11, 4 C. 11, 2.67 D. 10, 16
Posted by Civil Engineer
Asked on September 20, 2016 1:02 pm
0

C. 11, 2.67

Posted by Civil Engineer
Answered on September 20, 2016 1:05 pm
0

C. 11, 2.67