The distances AC and BC are measured from two fixed points A and B whose distance AB is known. The point C is plotted by intersection. This method is generally adopted in« Back to Previous Page

A. chain surveying B. traverse method of surveys C. triangulation D. none of these.
Posted by Civil Engineer
Asked on August 5, 2016 12:05 pm
0

A. chain surveying

Posted by Civil Engineer
Answered on August 5, 2016 12:06 pm