If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be« Back to Previous Page

A. started 5 days later B. completed 5 days later C. performed at slower rate in 15 days D. all the above.
Posted by Civil Engineer
Asked on August 30, 2016 2:28 pm
0

D.
all the above