The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as« Back to Previous Page

A. duration B. total flat C. free float D. interfering float
Posted by Civil Engineer
Asked on August 30, 2016 2:11 pm
0

C. free float


Posted by Civil Engineer
Answered on August 30, 2016 2:12 pm
0

C. free float


Posted by Civil Engineer
Answered on August 30, 2016 2:12 pm