The optimistic, most likely and pessimistic time estimates of an activity are 5, 10 and 21 days respectively. What are the expected time and standard deviation respectively ?« Back to Previous Page
A. 12, 3
B. 11, 4
C. 11, 2.67
D. 10, 16
|
▲ ▼ |
C. 11, 2.67 |
▲ ▼ |
C. 11, 2.67 |