In "full face" method of constructing tunnel, the first operation relates to« Back to Previous Page
A. removal to bottom portion
B. excavation of one drift in the centre
C. removal of top portion
D. excavation being done along the perimeter
|
▲ ▼ |
C. removal of top portion |
Please log in to post questions/answers: