While scheduling a project by C.P.M.« Back to Previous Page

A. a project is divided into various activities B. required time for each activity is established C. sequence of various activities is made according to their importance D. net work is drawn by connecting the activities and the events E. All the above.
Posted by Civil Engineer
Asked on August 31, 2016 12:59 pm
0

E. All the above.