If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be« Back to Previous Page
|
A. started 5 days later
B. completed 5 days later
C. performed at slower rate in 15 days
D. all the above.
|
| ▲ ▼ |
D. |
| ▲ ▼ |