If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be« Back to Previous Page
A. started 5 days later
B. completed 5 days later
C. performed at slower rate in 15 days
D. all the above.
|
▲ ▼ |
D. |
▲ ▼ |
D. |