The optimistic, most likely, and pessimistic estimates of time for an activity are 4 days, 11 days and 12 days respectively. The expected completion time of this activity is« Back to Questions List

A. 8 days B. 9 days C. 10 days D. 11 days
Posted by Civil Engineer
Asked on September 23, 2016 2:09 pm
0

C. 10 days