In PERT, the actual time duration along the critical path for the project completion time is probabilistic. It is usually presumed to follow which one of the following ?« Back to Previous Page

A. Beta distribution B. Poisson distribution C. Normal distribution D. Log-normal distribution.
Posted by Civil Engineer
Asked on September 23, 2016 1:35 pm
▲
0
▼

A. Beta distribution