• Measurement and Payment Schedule of Various Items

    by  • January 12, 2014 • 1000 Questions, Editorial, Scales • 0 Comments

    Units-Measurement-civil engineering

    Units-Measurement-civil engineering

    UNITS OF MEASUREMENT AND PAYMENT FOR VARIOUS ITEMS

    Sl. No.

     

     

    Particulars of items

     

     

    Units of measurement

     

     

    Unit of payment

     

     

    1

     

     

    Earthwork: Excavation, filling, cutting, banking

     

     

    m3

     

     

    100 m3

     

     

    2

     

     

    Surface dressing

     

     

    m2

     

     

    m2

     

     

    3

     

     

    Cutting of trees

     

     

    Number

     

     

    Per number

     

     

    4

     

     

    Stones: quarrying, blasting

     

     

    m3

     

     

    m3

     

     

    5

     

     

    Concrete : PCC, RCC, Precast

     

     

    m3

     

     

    m3

     

     

    6

     

     

    Jail works

     

     

    m2

     

     

    m2

     

     

    7

     

     

    Damp proof course

     

     

    m2

     

     

    m2

     

     

    8

     

     

    Brick work of any description

     

     

    m3

     

     

    m3

     

     

    9

     

     

    Thin partition wall

     

     

    m2

     

     

    m2

     

     

    10

     

     

    String course, drip course, water course coping etc

     

     

    m

     

     

    m

     

     

    11

     

     

    Stone work of any description

     

     

    m3

     

     

    m3

     

     

    12

     

     

    Stone work in wall facing (thickness specified)

     

     

    m2

     

     

    m2

     

     

    13

     

     

    Wood work: truss, rafter, beam etc

     

     

    m3

     

     

    m3

     

     

    14

     

     

    Door, window shutters

     

     

    m2

     

     

    m2

     

     

    15

     

     

    Door, window fittings

     

     

    Number

     

     

    Per number

     

     

    16

     

     

    Timbering, boarding, sawing of timber, timbering of trenches, partition, etc

     

     

    m2

     

     

    m2

     

     

    17

     

     

    Steel work

     

     

    Quintal

     

     

    Per quintal

     

     

    18

     

     

    Expanded metal, fabric reinforcement, cutting angles, plates, tees

     

     

    cm2

     

     

    cm2

     

     

    19

     

     

    Threading; welding; solder of sheets

     

     

    cm

     

     

    Per cm

     

     

    20

     

     

    Iron gate, grill collapsible gate, rolling shutter

     

     

    m2

     

     

    m2

     

     

    21

     

     

    Iron railing

     

     

    m

     

     

    m

     

     

    22

     

     

    Roofing: tiled, corrugated iron, caves board (thickness specified)

     

     

    m2

     

     

    m2

     

     

    23

     

     

    Centering, shuttering

     

     

    m2

     

     

    m2

     

     

    24

     

     

    Ridges; valleys; gutters (girth given)

     

     

    m

     

     

    m

     

     

    25

     

     

    Expansion and contraction joints

     

     

    m

     

     

    m

     

     

    26

     

     

    Ceiling timber, A.C. sheet, board, etc

     

     

    m2

     

     

    m2

     

     

    27

     

     

    Plastering; pointing; white washing; distempering; painting; varnishing; polishing; coal tarring; removing of paints

     

     

    m2

     

     

    m2

     

     

    28

     

     

    Flooring of any kind

     

     

    m2

     

     

    m2

     

     

    29

     

     

    Pipes, laying of pipes

     

     

    m

     

     

    m

     

     

    30

     

     

    Dismantling of brick masonry

     

     

    m3

     

     

    m3

     

     

    31

     

     

    Grouting

     

     

    m2

     

     

    m2

     

     

    32

     

     

    Grouting of cracks, joints

     

     

    m

     

     

    m

     

     

    33

     

     

    Supply of sand; brick ballast; aggregates; timber

     

     

    m3

     

     

    m3

     

     

    34

     

     

    Supply of cement

     

     

    Bag

     

     

    Per bag

     

     

    35

     

     

    Supply of steel, G.I. sheet, bare electric line

     

     

    Quintal

     

     

    Per quintal

     

     

    36

     

     

    Supply of GI sheet

     

     

    m2

     

     

    m2

     

     

    37

     

     

    Supply of sanitary items

     

     

    Number

     

     

    Per number

     

     

    38

     

     

    Supply of paint, varnishes

     

     

    Litre

     

     

    Per litre

     

     

    39

     

     

    Supply of explosives, stiff paint

     

     

    Kg

     

     

    Per kg